(BNP) - In Document No. 7873/UBND-KTN, the Chairman of the Provincial People's Committee directed relevant departments, localities, and units to accelerate the implementation of the road connecting Gia Binh Airport with Hanoi Capital (section passing through Bac Ninh province).
Illustrative photo.
Accordingly, based on the results of resolving outstanding issues and obstacles in land clearance, the Chairman of the Provincial People's Committee requested the People's Committees of communes and wards to urgently and closely coordinate with the Provincial Project Management Board for Transportation and Agriculture No. 2 to accelerate progress and focus on resolving all remaining outstanding issues and obstacles in land clearance implementation, ensuring the determination to approve compensation, support, and resettlement plans for the surveyed residential land area and organize appraisal according to regulations; The appraisal and approval process for the remaining land plots must be completed before July 31, 2026. Communes and wards should promptly appraise and approve the land plots that have sufficient legal basis.
The Chairman of the Provincial People's Committee assigns the Departments of Construction, Finance, Agriculture and Environment to proactively coordinate and promptly guide the compensation for land, assets, factories, and technical infrastructure for the land area to be acquired in Thuan Thanh III Industrial Park.
The Provincial Project Management Board for Transportation and Agriculture No. 2 should continue to accelerate the relocation of technical infrastructure; urgently construct the resettlement area in Lam Thao commune to ensure adequate conditions for relocating residents; and continue to hand over the cleared land to the investor for construction.
The People's Committees of Thuan Thanh, Tram Lo, Tri Qua, and Mao Dien wards are focusing on accelerating the implementation of resettlement projects, expanding the People's Cemetery, rebuilding cultural centers, repairing schools and related facilities… to ensure conditions for resettlement, relocation of graves, and early stabilization of people's lives in the project area.
The Chairman of the Provincial People's Committee assessed that the investor's preparation and construction organization are still slow. Without more decisive solutions, it will be difficult to ensure the progress for the APEC 2027 Conference. Based on the amount of land already handed over (304.4/412.6 hectares of land have been handed over, reaching 74% of the area), the Chairman of the Provincial People's Committee requested the investor to urgently accelerate preparation work, mobilize maximum machinery, equipment, and personnel; We will develop a scientific construction plan, deploy multiple construction fronts simultaneously, maintain continuous construction in 3 shifts and 4 teams, and strive to complete the project on schedule as required and directed by the Party and State leaders.